  • Project Name: Hot Mix Asphalt Shim & Overlay 2025
  • Project Description: Resurface the following roadways:
  • Cherdon Lane
  • Thayer Street
  • Norwood Court
  • Virginia Lane
  • Maple Avenue
  • North Water Drive
  • Old Depot Road
  • Depot Road (Main St – Old Worcester Rd)
  • Newton Avenue
  • Millbury Road (28 Millbury Rd – Federal Hill Rd)
  • Millbury Boulevard
  • Project Goals: Resurface the listed roadways to provide a smoother and more robust driving surface.
  • Location: List above.
  • Construction Begins: Summer 2025    
  • Construction Ends: Summer 2025    
  • Contact Person: Peter Gerhard, Assistant Director of Public Works   
  • Cost:  $556,805   