Project Description:Reconstruct the Main Street corridor from Fairlawn Avenue to Front Street with accessible sidewalks and ramps, separated bike facilities, transit bus stops, traffic calming measures, and traffic signal upgrades at the downtown intersection.
Project Goals:Reimagine Oxford's downtown to promote multimodal travel and develop a safer, more accessible corridor for all modes and roadway users of all abilities.
Location:Main Street from Front St. to Fairlawn Ave.
Construction Begins: Winter 2028
Construction Ends:Fall 2030
Contact Person:Kevin Duffy, Director of Public Works
Cost:$17,746,000 (January 2026)
Contractor:Design Engineer - The Engineering Corp.
Current Status:
25% Design submitted to MassDOT for review December 2024
Design Public Hearing - Tuesday January 13th at 6:30 PM (see links below)