Complete Project Name: Hot Mix Asphalt Shim & Overlay FY2025
Project Description: The Town resurfaced the road pavement on Walnut Street with a shim and overlay, and an overlay on a portion of Brown Road. Both the shim and overlay consist of hot mix asphalt (HMA). The road was shimmed with HMA to create a uniform cross section, and then overlayed with HMA to create the new driving surface.
Project Goals: Provide a uniform cross section and profile on the roadway to the extent feasible, provide structural improvement, reduce wear & tear on Town’s fleet, and significantly improve rideability for all roadway users.
Location: Walnut Street form Pine Street to Dudley Road, #9 to #19 Brown Road
Construction Begins: Summer 2024
Construction Complete: Summer 2024
Contact Person: Peter Gerhard, Asst. Director of Public Works
Cost: Walnut Street - $222,600; Brown Road - $48,000