• Project Name: Town Wide Crack Sealing
• Project Description: Crack Sealing of various roadways throughout Town
• Project Goals: The primary goal of crack sealing roadways is to prevent water from entering cracks in the pavement, which can significantly deteriorate the road base. This is done to extend the lifespan of the asphalt by stopping further crack propagation, ultimately saving money on major repairs by addressing small cracks early on.
• Location: Depot Rd., Harwood Rd., Leicester St. from Rt. 20 to Mill, Comins Rd., Mount Pleasant St., Heritage Rd.
• Construction Begins: Fall 2024
• Construction Complete: Fall 2024
• Contact Person: Peter Gerhard, Asst. Director of Public Works
• Cost: $24,947.75
• Contractor: Indus Corp.